Underground Piping, SPGFD Phase 13

Underground Piping of South Pars Gas Field Development Phase 13 is done by Radira Company and the Construction Management of this project is done by VASTAPAD Company.

Major Quantities of Work
Activity Qty. Unit
Excavation 680,000
Backfill 445,000
Sand fill 142,000
Concrete 8,000
GRP Piping 151,000 Dia-Inch
C.S. Piping 25,600 Dia-Inch
Gal. Piping 9,000 Dia-Inch

Project Details

DATE

Aug. 2011 ~ Jun. 2014

MAIN CIENT

Petro Paydar

PROJECT TYPE

Construction Management

CONTRACT VALUE

$ 18,000,000 (Construction Management)

SKILLS REQREQUIRED 

Civil
Piping