Underground Piping, SPGFD Phase 13
Underground Piping of South Pars Gas Field Development Phase 13 is done by Radira Company and the Construction Management of this project is done by VASTAPAD Company.
Major Quantities of Work
| Activity | Qty. | Unit |
|---|---|---|
| Excavation | 680,000 | m³ |
| Backfill | 445,000 | m³ |
| Sand fill | 142,000 | m³ |
| Concrete | 8,000 | m³ |
| GRP Piping | 151,000 | Dia-Inch |
| C.S. Piping | 25,600 | Dia-Inch |
| Gal. Piping | 9,000 | Dia-Inch |
Project Details
DATE
Aug. 2011 ~ Jun. 2014
CLIENT
MAIN CIENT
PROJECT TYPE
Construction Management
CONTRACT VALUE
$ 18,000,000 (Construction Management)