Control system and ACC Tang Zagh iron ore concentrate factory

Tang Zagh iron ore mine is located 110 km from Bandar Abbas. Phase 1 Exploitation of this mine was put into operation in 1399 with the construction of a concentrate factory by the esteemed employer of Tang Zagh Iron Ore Company. Preparation and implementation of control system and ACC This factory was assigned to Vesta Pod Alborz Company after holding a tender, and this company was able to prepare, manufacture and prepare the relevant control system and ACC within 45 days by using its engineering power and supply of goods. And all the documents prepared for the project, which amounted to 500 sheets of engineering degree, were delivered to the employer in the form of FINAL BOOK.
Starting a project that includes preparing the control room, setting up computers and control panels, testing each input and output signal, starting the motors and commanding the valves separately, and finally group start of the system and adjusting the analog values ​​according to According to the Set point & Alarm List document, it was done in less than a month and the system was completely delivered to the employer.
Finally, after-sales service was provided to the employer in person or remotely (from Tehran office by REMOTE ACCESS method).

Major Quantities of Work
Activity Qty. Unit
Buy 35,566 Euro
Engineering drawings and documents 500 Page
Programming 350 Hours
Build 200 Hours

Project Details

DATE

Apr.2020 – Aug.2020

CLIENT

Tang Zagh Iron Ore Company

PROJECTS SITE

Tang Zagh